This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging crews poured the third section of the top floor concrete deck this past week. The CMC crews also commenced with the installation of post tension cables and reinforcing steel for the fourth section of the top floor concrete deck.

HDCC crews pouring the third section of the top floor concrete deck of the parking structure
CMC crews installing post tension cables and reinforcing steel for the fourth section of the top floor concrete deck
Aerial photos of the parking structure

Vineyard Street Improvements:
The MIRA crews continued with the concrete curb and sidewalk work for the street this week. The MIRA and Wasa Electric crews also commenced with the installation of the last section of underground electrical and communication conduits this past week.

MIRA crews excavating for last section of electrical and communication conduits
MIRA crews pouring concrete curbs and sidewalks

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.