HOA Construction Update – April 10, 2026

Work at the Hālau of ʻŌiwi Art site progressed into the next phase this week, with crews beginning preparation and forming for the second round of tilt-up panels. Site activity focused on layout, forming, and readiness for upcoming installation, while also addressing safety measures in advance of anticipated weather conditions.

Pictured above: F&H crews begin forming for the second phase of tilt-up panels.

F&H Crews started forming 2nd phase of panels.

RD laying out

F&H Crews cleaning up site and getting ready for the next phase of tilt up panels.

Certified Welding prepping to weld panels.

F&H crews reinforcing job site perimeter fence, before this weekend's 3rd round storms.