HOA Construction Update – July 24, 2026

Work this week included concrete pours, site preparation and the first installation of structural steel at the Hālau of ʻŌiwi Art site.

Pictured above: F&H poured walls and columns at Retail Buildings 1 and 2.

‍

F&H poured curbs outside the electrical room.

‍

TB backfilled and compacted the loading dock area.

‍

The first delivery of structural steel arrived on site July 21.

‍

The first structural steel beams were installed July 24.

‍