HOA Construction Update – May 8, 2026

Construction progress continued this week at the Hālau of ʻŌiwi Arts, with crews completing a major tilt-up panel pour and continuing preparation work across the site. Reef Development, H&H, and F&H crews advanced key structural elements, including panel pours, formwork, embeds, and cast-in-place wall forms in the retail space area.

Pictured above: Reef Development and H&H crews pour 13 tilt-up panels, totaling 110 cubic yards of concrete.

Site photo after the panel pour.

Site photo after the panel pour.

Reef Development installing formwork and embeds.

Reef Development and F&H installing Cast In Place wall forms in the Retail space area.