HOA Construction Update – October 16, 2026

This week’s construction activities at Hālau of ʻŌiwi Art in Wailuku included underground plumbing installation, electrical rough-in work, structural steel column installation and concrete pours in the future courtyard area.

Pictured: F&H crews pour concrete columns in the future courtyard area.

Dorvin D. Leis crews install underground plumbing in Workshop 1, coordinating with Tom’s Backhoe on backfilling operations.

‍

Alaka‘i Electric crews perform electrical rough-in work in Retail 5 and 6 and Workshop 2.

‍

Certified Welding crews install hollow structural section (HSS) steel columns.

‍

‍

‍