HOA Construction Update – October 2, 2026

Construction continues on the new Hālau of ʻŌiwi Art (HOA Maui) at Vineyard Street and North Church Street in Wailuku. This week, crews focused on backfilling and compaction, rebar installation, concrete pouring, and formwork for the future pedestrian bridge connecting the facility to the Wailuku Parking Garage. You can also follow construction activities through the live video feed at www.wailukulive.com/hoa.

General Notices

Construction on HOA Maui began on April 28, 2025, and is scheduled for completion by April 19, 2027, subject to change. Please expect typical commercial construction noise during this period. For questions, contact F&H Construction Superintendent Terry at 808-495-7952.

Pictured above: CMC crews installed rebar on Level 2 above the loading dock.

‍

Tom’s Backhoe crews backfilled and compacted areas on Level 1, including Retail 2, Retail 5, and Workshop 2.

‍

Reef Development and F&H Construction crews poured concrete for the Level 2 deck.

‍

F&H Construction crews installed formwork for the future pedestrian bridge connecting HOA Maui to the Wailuku Parking Garage.