Work at the Hālau of ʻŌiwi Art site was impacted by frequent rain throughout the week, limiting overall productivity. Crews took advantage of drier periods early in the week to continue formwork, embeds, and rebar installation, along with stripping panel forms from the previous pour. Despite weather delays mid to late week, progress continues as crews prepare for the next phase of construction.
Pictured above: On March 9, F&H crews installing formwork and embeds, and stripping formwork.