Construction activity at the Hālau of ʻŌiwi Art site progressed early in the week with crews focused on tilt-up panel preparation, including formwork, embeds, and footing work. Midweek and end-of-week rain events temporarily paused operations, but crews were able to make steady progress in between weather delays, preparing for upcoming pours and continuing structural groundwork near Vineyard Street.
Pictured above: RD crews stripping forms in preparation for Friday’s pour.