LATEST UPDATES

HOA Maui Construction Update – March 6, 2026

Construction at the Hālau of ʻŌiwi Art site moved forward with strong coordination across multiple crews as preparations were completed for a major tilt-up panel pour. Work throughout the week focused on formwork, embeds, trench backfilling, and finalizing rebar, electrical, and plumbing installations. These efforts culminated in the successful pour of multiple tilt-up panels, marking an important step in vertical progress on the project.

Pictured above: F&H and RD crews installing formwork and embeds for tilt-up panels.

TB backfilled and compacted the trench for the 18-inch drain line.

Rebar, electrical, and plumbing crews working to complete installations ahead of the tilt-up panel pour.

Special Inspector inspecting installed rebar.

F&H and RD crews poured 14 tilt-up panels.

Site photo.