This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews completed the installation of reinforcing steel and post tensioning cables for the second section of the fourth-floor concrete deck. The fourth-floor concrete deck will be poured next week.  The Maui Kupono crews continued with the preparatory work for the third and fourth sections of the parking structure ground floor concrete slab this week.

Maui Kupono crews grading site for the ground floor concrete pavement
HDCC crews setting concrete wall forms
CMC crews completing installation of reinforcing steel and post tensioning cables for the fourth-floor concrete deck

Vineyard Street Improvements:
The MIRA and Wasa Electric crews continued with the installation of the underground electrical and communication infrastructure work this week. Work on the new streetlight infrastructure also commenced this week.

Mira and Wasa Electric crews installing concrete streetlight bases and conduits.
Mira and Wasa Electric crews installing electrical and communication pull boxes and ductlines.

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, click here.