Wailuku Parking Structure
The HDCC crews completed the remaining concrete work on the top floor of the entrance structure this week. The HDCC subcontractor crews continued with the finishing work on the interior of the parking structure. The asphalt concrete driveway from Vineyard Street was paved this week.

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.

Maui Kupono crews paving driveway from Vineyard Street
JD Painting crews painting pavement markings
JD Painting crews painting structure