This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging crews poured the third section of the third- floor concrete deck this past week. The Hawaiian Dredging and CMC crews also commenced with the installation of post tension cables and reinforcing steel for the fourth section of the third-floor concrete deck of the parking structure.

Hawaiian Dredging crews pouring third-floor concrete deck
CMC crews installing reinforcing steel for the fourth section of the third-floor concrete deck
Hawaiian Dredging crews setting concrete wall forms for parking structure entrance
Maui Kupono crews grading the Pili Street entrance

Vineyard Street Improvements:
The MIRA crews continued with the concrete curbing, sidewalk and driveway work for the street this week.

MIRA crews backfilling completed concrete curbs
MIRA crews setting concrete curb forms

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.