This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews completed the installation of post tensioning cables and reinforcing steel for the for the second floor of the fourth section of the parking structure this week. The Hawaiian Dredging crews will be pouring this section of the concrete deck next week. The Hawaiian Dredging crews also commenced with the setting of the third-floor concrete beam formwork for the third section of the parking structure.

Hawaiian Dredging and CMC crews completing the installation of post tensioning cables and reinforcing steel for the second-floor concrete deck
Hawaiian Dredging crews setting concrete beam formwork for the third floor
Hawaiian Dredging and CMC crews setting reinforcing steel for the parking entrance structure foundation
Aerial photo of the Project

Vineyard Street Improvements:
The MIRA crews continued with the concrete curbing and sidewalk work for the street this week.

MIRA crews grading and setting forms for the new concrete curbs and sidewalks
MIRA crews pouring new concrete curbs and sidewalks

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.