This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews continued with the setting of concrete beam and deck forms, post tensioning cables and reinforcing steel for the second floor of the third section of the parking structure this week. The Hawaiian Dredging crews also poured the last major section of the parking structure ground floor concrete slab this week.

Hawaiian Dredging and CMC crews setting forms and reinforcing steel for the second floor concrete deck
Hawaiian Dredging crews pouring the last major section of the ground floor concrete slab

Vineyard Street Improvements:
The MIRA and Wasa Electric crews continued with the installation of the underground electrical and communication infrastructure this week. The MIRA crews also continued with the concrete curbing work for the street.

MIRA and Wasa Electric crews installing electrical and communication ductlines
MIRA crews forming concrete curbs

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.