Wailuku construction update

This week’s construction update

Wailuku Parking Structure:

The Hawaiian Dredging crews began installing the concrete beam and deck forms for the third floor this past week. The HDCC and CMC crews also continued work on the second-floor concrete columns and walls.   

HDCC crews installing concrete beam and deck forms for the third floor
HDCC crews installing concrete wall forms
HDCC crews pouring second floor concrete columns and walls
HDCC crews pouring concrete curbs at First Hawaiian Bank

Vineyard Street Improvements:

The MIRA crews continued with the installation of the sewer system improvements on Vineyard Street between Church and High Street this past week. The new sewer mainline has been completed and the MIRA crews are installing new sewer laterals to each of the properties along Vineyard Street.

MIRA crews working on Vineyard Street sewer system replacement
MIRA crews excavating for new sewer laterals
MIRA crews backfilling new sewer lateral connection to property

General Notices:

Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm. 

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway, Wells Park and War Memorial Stadium Parking Lot) and various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please visit www.wailukulive.com.