This week’s construction update

Vineyard Street Improvements:
The MIRA surveying crews began the layout of the drainage and electrical system improvements this past week. Work on these improvements will commence next week.

Mira surveyors laying out drainage and electrical system improvements


Wailuku Parking Structure:
The Hawaiian Dredging crews poured the second section of the third-floor concrete deck this week. The first section of the third-floor concrete columns and walls were also poured this week.

Maui Kupono demolishing the existing Pili Street sidewalks and roadway pavement
HDCC crews pouring third-floor concrete wall
HDCC crews pouring concrete for the second section of third-floor concrete deck
HDCC crews pouring concrete for the second section of third-floor concrete deck
HDCC crews finishing the second section of the third-floor concrete deck

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway, Wells Park and War Memorial Stadium Parking Lot) and various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, click here.