Wailuku construction update

This week’s construction update

Wailuku Parking Structure:

The Hawaiian Dredging crews continued with the installation of concrete beam and deck forms for the third floor this past week. The installation of reinforcing steel and post tensioning cables for the third-floor deck is also underway.

Maui Kupono crews demolishing existing sidewalks and removing existing drain system

HDCC crews removing second-floor concrete beam and deck forms
HDCC crews setting the third-floor concrete beam forms.

HDCC and CMC crews installing reinforcing steel and post tensioning cables for the third-floor concrete deck

Vineyard Street Improvements:

The MIRA crews completed the installation of new sewer laterals to each of the properties along Vineyard Street this week.

MIRA crews installing reinforcing steel for sewer lateral concrete jacket
MIRA crews pouring concrete jacket for sewer lateral
MIRA crews backfilling sewer lateral trenches

General Notices:

Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm. 

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway, Wells Park and War Memorial Stadium Parking Lot) and various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please visit www.wailukulive.com.