This week’s construction update

Vineyard Street Improvements:
The MIRA crews completed lowering the existing water service laterals to each of the properties this week.

MIRA crews installing new water service laterals
MIRA crews installing new water service laterals
MIRA crews excavating the existing water service laterals

Wailuku Parking Structure:
The Hawaiian Dredging crews continued with work on the second section of the third-floor concrete deck this week. Work on the third-floor columns and walls also commenced this week.

Maui Kupono crews backfilling foundations and the parking structure entrance along Church Street
HDCC and CMC crews installing reinforcing steel for the concrete column
Parking structure third floor concrete deck
Parking structure third floor concrete deck

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway, Wells Park and War Memorial Stadium Parking Lot) and various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, click here.