HOA Maui Construction Update – November 21, 2025

Progress continued this week at the Hālau of ʻŌiwi Art construction site, with crews making steady headway despite a mid-week rainout. Work focused on foundational preparation, utility installation, and ongoing structural setup as teams kept the project moving forward. Follow our progress on our live cam at https://www.wailukulive.com/hoa.

F&H crew continued stripping footing forms

Tom’s Backhoe Excavating installed a sewer manhole and continued work on the sewer lines

F&H crew continued to install footing forms