HOA Maui Construction Update – October 31, 2025

Progress continues at the Hālau of ʻŌiwi Art site as crews work steadily on key structural and utility installations. Teams are coordinating efforts across several areas to advance construction. Follow along anytime at www.WailukuLive.com/HOA to visit our live cam.

CMC Rebar crews begin installing footing rebar.

F&H Construction continues setting footing forms.

Beachside Roofing applies waterproofing in the elevator pit.

Tom’s Backhoe works on installing drain lines and manholes.